University of East Anglia

Contractor: RG Carter

New development: Large modern student accommodation 

1st phase 

Removed the asbestos and stripped out, dismantled and demolished four storey concrete block living accommodation making sure to leave a clean site. This phase was successfully finished two weeks ahead of time.

 

2nd phase 

Working in a populated environment Fincham dismantled the old building from the new building, which was only 7 ft away without causing it any damage. This job was completed two weeks ahead of time also.